Pamphlet 26-7,Chapter 14 Construction Inspections

14.02  Inspection Stages, Continued

 

Individual Water Supply and Sewage Disposal System

Individual Water Supply and Sewage Disposal System

 

The inspector will include with the inspection report evidence obtained from the builder that installation in satisfactory to the health authority having jurisdiction.

 

Final Inspection

Generally, this coincides with the third inspection stage and requires the Compliance Inspection Report, VA Form 26-1839 to  

 

·   include two photographs (preferably taken from the diagonally opposite front and rear corners) to record the appearance of the dwelling and indicate the grading and drainage of the site

·   describe the condition, suitability, and readiness for use of all equipment, fixtures and observable construction of the property

·   report shortcomings such as scratches in painted surfaces, poorly fitted doors, stuck windows, cracks in walls, irrespective of any arrangements made on the site for corrections, and

·   confirm that any instance of inferior workmanship, defective materials or equipment, or faulty installation or application of materials or equipment and/or deviation from approved plans and specifications is reported on VA Form 26-1839, and

·   if the property is a unit on a master appraisal either

-   clearly identify any optional variation or item of equipment included in the construction, or

-   state that none is included.

 